How should I split bug fixes into milestones for a Go microservice?
With Tares, you split bug fixes into milestones that each end on acceptance checks you can confirm, such as tests and CI first, then the fixes, then merge and deploy. The software factory for Claude Code plans a project as milestones with checks, then tickets inside them. The spec session proposes the milestones and you review them before you hand the project to the crew. The end of each milestone is where the orchestrator brings you the choices the crew made on its own.
How it works
A project in the software factory for Claude Code is planned as milestones, and each milestone carries acceptance checks. Tickets sit inside a milestone. A builder works through them one at a time: it makes a branch, does the work and opens a pull request. The reviewer reviews every pull request, and the builder merges once the verdict passes and CI is green.
The worked example in A project, end to end is a pull request with no tests and a few bugs. Its spec session produced three milestones:
- M1, tests and CI on the branch. A test runner, unit tests for the buggy logic, and a CI check on every pull request.
- M2, payout history stays as it was. The bug fixes, stated as an outcome you can check: deactivating a sitter or changing a rate leaves past weeks as they were.
- M3, merged and live. The pull request documented, merged into main and running in production.
That project used a different stack, but the shape carries over to bug fixes in a Go microservice: first make the fixes checkable, then fix, then ship. Each milestone is named for the state it leaves behind, not for the work inside it.
Where a milestone ends matters because of assumptions. When the crew meets something the plan does not cover, it picks the sensible answer, writes it down as an assumption and carries on. At the end of each milestone the orchestrator brings you its assumptions in one question. In the example, a working doc named a config file that failed to load on the repo’s Node version, so the builder used another one and recorded it. You answered once per milestone.
The plan can also grow. The reviewer found smaller issues outside the ticket it was reviewing, and the orchestrator turned them into a new ticket placed inside M2, before the integration tests.
Set it up
Run the steps in this order. Skip the ones you have already done.
- Check that Claude Code is signed in, that
ghis signed in with write access to the repos the crew works in, and that git is installed. - Install the CLI.
- On a local Tares, start Tares, then start the MCP endpoint every crew session shares in a second terminal. On Tares Cloud, run
tares loginand pick your workspace in the browser instead. There is no MCP endpoint to start. - Give Tares access to GitHub: in Settings > GitHub for a local Tares, or with Connect GitHub on Tares Cloud.
- Bring up the crew.
- Plan the project with
tares factory spec, run in your service’s repo. Describe the bugs you want fixed, then answer Claude Code’s questions. A second model challenges the plan, and the result lands in Tares as a spec, a plan, an AGENTS.md and milestones with acceptance checks. - Open the project page and read the Tickets fold. Check that each milestone ends on checks you can confirm, then say yes to hand the project to the crew.
gh auth login
uv tool install tares # or: brew install glassflow/tap/tares
tares up # local Tares only
tares mcp --transport streamable-http # local Tares only, in a second terminal
tares login # Tares Cloud only
tares factory crew up
tares factory spec "what you want to build"New to the factory? Get started covers the first run in full.
What you get
- A plan you can check. The Tickets fold lists milestones with their acceptance checks, and each ticket with its builder, its pull request and its review rounds.
- One confirmation per milestone. The orchestrator brings the assumptions the crew made in that milestone together in one question. Each assumption names its tickets and the builder that made it. To make an answer stand from now on, say so, for this project or for every project.
- A record of every decision. The Decisions fold holds each question the crew asked and your answer in your own words. The Assumptions fold shows each choice and whether you kept it.
- Visible progress. The project page shows Spec, Build, Review and Done, with one progress bar segment per ticket. A blocked ticket names the tickets it waits for.
- A finish you control. After the last milestone the orchestrator asks whether the project is finished. Tares marks it Done with your words and moves it to the finished list on the Crew page.
When something else fits
- If the fix is a single small change, one milestone with one ticket is enough. Extra milestones add questions without adding safety.
- If you want to steer a ticket that is already in progress, talk to the orchestrator instead of re-planning. The page lists the questions waiting for you too.