How should I split framework migrations into milestones for a Go microservice?
Tares plans work as milestones with acceptance checks, so split a Go framework migration into outcomes you can check, not into layers of code. Each milestone ends when its tickets are merged and its acceptance checks pass, which the builders and the reviewer verify. The orchestrator then starts the next milestone, and brings you the assumptions the crew made in one question that you answer at your own pace.
How it works
A project in the software factory for Claude Code holds milestones, and each milestone carries acceptance checks. Each milestone holds tickets. A builder works the tickets one at a time: it makes a branch, does the work and opens a pull request. The reviewer reviews every pull request and posts a verdict. Once the verdict passes and CI is green, the builder merges.
A milestone counts as done when its tickets are merged and its acceptance checks pass. The orchestrator then starts the next milestone. The project in A project, end to end used three milestones, each named for the outcome it proves:
- M1, tests and CI on the branch. A test setup, unit tests for the logic at risk and a CI check on every pull request.
- M2, behavior stays as it was. Specific behaviors that must not change.
- M3, merged and live. Documented, merged into main and running in production.
For a framework migration in a Go microservice, the same shape is a useful starting point:
- First milestone: a safety net. Tests and a CI check that run on every pull request, before any framework code changes.
- Middle milestones: one slice each. Pick slices that can be merged and checked alone, for example the handlers of one route group, then the middleware, then configuration and startup. Write acceptance checks that say what must still behave the same.
- Last milestone: merged and live. The migration is documented, merged into main and running in production.
A milestone that ends in something you can verify gives the reviewer and the builders a clear finish line. If a check cannot fail, the milestone is too vague.
When the crew meets something the plan did not cover, it picks the sensible answer, writes it down as an assumption and carries on. The example project recorded a choice like this: the working doc named a config file that failed to load on the repo’s Node version, so the builder used a different one. At the end of each milestone the orchestrator brings you that milestone’s assumptions in one question, and you keep or reject them. That question does not hold up the next milestone. If you reject an assumption, say so and the crew works from your answer from then on.
Set it up
- Check that Claude Code is signed in, that
ghis signed in with write access to the repos the crew works in, and that git, jq and curl are installed. - Install the CLI, start Tares locally, and in a second terminal start the MCP endpoint every crew session shares. On Tares Cloud, run
tares logininstead of the local start and the MCP endpoint. - Give Tares access to GitHub, in Settings > GitHub for a local Tares.
- Bring up the crew.
- Plan the project from the repo of your Go service. Describe the migration in the spec prompt, and answer Claude Code’s questions about it.
gh auth login
uv tool install tares # or: brew install glassflow/tap/tares
tares up
# in a second terminal:
tares mcp --transport streamable-http
tares factory crew up
tares factory spec "what you want to build"- In the spec session, shape the milestones. Ask for one outcome per milestone and for acceptance checks that you can verify. A second model challenges the plan, and the result goes into Tares as a spec, a plan, an AGENTS.md for the project and the milestones with their checks.
- Say yes to handing the project to the crew. The orchestrator picks it up and starts a builder for the first milestone. New to the factory? Start with Get started.
What you get
- A plan you can read. The Tickets fold on the project page shows milestones with their acceptance checks, and each ticket with its builder, pull request and review rounds.
- Milestones that close on checks. The reviewer reviews every pull request, and CI must be green before a builder merges.
- A plan that adapts. In the example project the reviewer found smaller issues outside the ticket in review, and the orchestrator turned them into a new ticket placed in the milestone before its integration tests.
- A record of the crew’s choices. The Assumptions fold lists every choice the crew made on its own and whether you kept it. The Decisions fold keeps each answer you gave in your own words.
- A progress view. The project page shows Spec, Build, Review and Done, with one progress segment per ticket.
- A clean finish. After the last milestone the orchestrator asks whether the project is finished. Tares marks it Done with your words.
When something else fits
- A migration that is a single small change does not need several milestones. One milestone with clear acceptance checks keeps the plan short.
- If you want a fixed order of work in one repo and nothing else, steer the orchestrator directly with the questions it asks, rather than splitting the work further.
- If a slice cannot be merged and checked alone, merge it with its neighbor into one milestone so that each milestone ends on something you can verify.